Dillinger Fundamente für EAF
05 November 2026

Foundations for the Electric Arc Furnace in Dillingen

Dyckerhoff Concrete Supplies One of Europe’s Most Ambitious Transformation Projects in the Steel Sector

Power4Steel: Transformation of the Saarland Steel Industry
A groundbreaking project for the future is currently underway at the industrial site of Aktien-Gesellschaft der Dillinger Hüttenwerke, Europe’s leading manufacturer of heavy plate. As the project owner, SHS - Stahl-Holding-Saar (together with its subsidiaries Dillinger, Saarstahl, and ROGESA) is implementing the ambitious “Power4Steel” transformation project at the Dillingen and Völklingen production sites.

By the early 2030s, approximately 70% of production is expected to be converted, resulting in a reduction of about 55% in CO₂ emissions. This corresponds to an annual reduction of approximately 4.8 million metric tons of CO₂. The SHS Group’s long-term goal is to achieve fully climate-neutral production by 2045 under the “Pure Steel+” brand. Further information on the transformation and the new brand is available on the website www.pure-steel.com

This overall project, totaling 4.6 billion euros and including infrastructure and logistics, is primarily financed by federal and state funds amounting to 2.6 billion euros, as well as through a successfully completed major financing deal and substantial equity capital. Important conditions are also being established for the future hydrogen supply: supply contracts and agreements for transport via cross-border pipelines are intended to secure the supply to the direct reduction facility in Dillingen.

The Core Facilities: Direct Reduction Facility and Electric Arc Furnaces
The core facilities of this project are a state-of-the-art direct reduction facility (DR facility) on the Dillingen plant site, as well as a new electric arc furnace (EAF) at each of the Dillingen and Völklingen locations. The DR facility at the Dillingen site will supply the plants in Dillingen and Völklingen. In the future, directly reduced iron—also known as DRI or iron sponge—will be produced there from ore. Natural gas will be used initially. As soon as sufficient hydrogen is available, production will be gradually converted to hydrogen. This key technology breaks with the traditional, coal-based blast furnace process and, together with the new electric arc furnaces, enables a significant decarbonization of the Saarland steel industry.

Large-scale concrete placement for the EAF: approximately 6,000 m³ of concrete in 38 hours
The construction of the massive foundation for the electric arc furnace in Dillingen placed high demands on everyone involved in the project and required precise coordination between construction site logistics and concrete technology. An additional challenge was that the construction work had to be carried out while the plant remained in operation. The EAF-Halle Dillingen consortium (ARGE), consisting of the companies Peter Groß Hochbau GmbH & Co. KG and Ed. Züblin AG, is responsible for the construction of the foundation.

The tight schedule for the concreting work posed a particular challenge: In a 38-hour marathon from April 28 to 29, 2026, approximately 6,000 m³ of concrete in strength classes C30/37 and C50/60 with consistency class F5 was installed in continuous operation.

To reliably supply this extraordinary volume on schedule, four ready-mixed concrete plants collaborated as a supply consortium: the Saarlouis plant of the contractor GROSS-th-beton GmbH & Co. KG, the Rehlingen plant of Mobil-Beton GmbH, and two Dyckerhoff locations. In addition to the Dillingen ready-mixed concrete plant, located just three kilometers from the construction site, Dyckerhoff also supplied concrete from its Merzig plant.

All parties involved thus made a significant contribution to ensuring a smooth supply to the construction site and efficiently coordinated logistics. The concrete was placed using up to three pumps simultaneously; on average, approximately 150 m³ of concrete was processed per hour. In total, approximately 830 truckloads were delivered to the construction site, which covered an area of approximately 320,000 m².

Concrete Technology for Demanding Foundations
The concrete used for the foundations of the EAF hall meets exposure classes XC4, XD2, XS2, XF2, XF3, and XA2. It was produced using blast furnace cement, which contains up to 80% blast furnace slag and a low Portland clinker content of 34% maximum. A total of approximately 2,000 metric tons of Dyckerhoff AQUADUR [CEM III/B 42.5 L-LH/SR (na)] from the Dyckerhoff cement plant in Amöneburg was used.

Due to its properties, this cement is particularly suitable for massive structural elements and demanding foundations and meets the high requirements for load-bearing capacity and durability of the foundations for the electric arc furnace as well as the foundations of the DR facility.

Additional Foundations in the Transformation Project
In the meantime, additional foundations for plant components have been or are being constructed using concrete from Dyckerhoff as part of the transformation toward low-carbon steel production. The concrete mixes used are primarily based on AQUADUR from Amöneburg and CEDUR [CEM II/C-M (S-LL) 42.5 N (na)] from the cement plant in Göllheim. The total concrete requirement for the construction project amounts to 300,000 m³.

Construction work on the foundations is scheduled to be completed by mid-2027.

Photos: SHS - Stahl-Holding-Saar GmbH & Co. KGaA / Jörg Klein

For further information please contact:
Iris Weise-Rosch, Tel.: +49 611 676-1187
marketing@dyckerhoff.com