The world’s first prestressed concrete bridge built using the cantilever method was constructed in Balduinstein on the Lahn River in 1951. After 75 years of service, it had sustained significant damage, making a replacement necessary.
Dyckerhoff concrete made with cement from the Neuwied plant was used to build the new Lahn Bridge in Balduinstein. Concrete grade C 40/50 F 3 16 was used for the superstructure. The cement used was HOZ Doppel CEM III/A 42.5 N. Its moderate heat of hydration can help reduce thermal stresses and cracking in the concrete. In addition, its low water demand and good water-retention capacity help reduce what is known as “bleeding” in fresh concrete and improve its workability. Around 1,700 m³ of concrete was specified for the project as a whole; about 500 m³, the largest share, was used for the superstructure of the new bridge.
A nighttime concrete pour was required on September 3, 2025, for the superstructure; that is, the upper, load-bearing part of the new bridge. The contractor, Albert Weil AG of Limburg, began placing the concrete at 3 a.m. Two 47-meter-long boom pumps were used to place the concrete from both riverbanks, using two Putzmeister M47 iONTRON hybrid pumps supplied by Dyckerhoff. The placement rate reached up to 85 m³ of concrete per hour. A total of 19 mixer trucks were in operation. The concrete was mixed at the Hadamar and Mogendorf plants, while the cement used came from Dyckerhoff’s Neuwied plant.
The new road bridge crosses the Lahn River in Balduinstein, a local municipality in the Rhein-Lahn district of Rhineland-Palatinate. The project owner is Landesbetrieb Mobilität (LBM) Diez. Construction of the replacement bridge began in early July 2024. The bridge is designed to carry vehicles weighing up to 40 metric tons. Total construction costs are approximately €8.2 million.
Traffic has been crossing the Lahn Bridge again since early August 2026. This marks an important milestone, even though work is not yet fully complete. The old bridge has already been demolished. The project was originally expected to take about two and a half years to complete.
The new bridge replaces a structure of particular significance in the history of bridge construction. Designed by Ulrich Finsterwalder and built by Dyckerhoff & Widmann, it was constructed in 1950 and 1951 without falsework.
The replacement brings the Lahn crossing in Balduinstein up to today’s standards. By placing the concrete for the superstructure, Dyckerhoff made a contribution to a project at a site that had already made history many decades earlier with a pioneering prestressed concrete bridge.